Hi! I'm working on a plot to show the displacements of a point at different times and I got the following:
I got the results I wanted on the plot but instead of showing the time in julian time, I want to show the date. I tried converting the time vector using the datestr command but it says that there is a subscript mismatch. Can someone help me with this? Thank you.

采纳的回答

Walter Roberson
Walter Roberson 2017-9-13
If you have roughly R2015b or later (I would need to recheck the exact release) then where you have roughly
plot(Time, Displacement)
change that to
TimeDT = datetime(Time, 'ConvertFrom', 'juliandate', 'Format', 'yyyy-MM-dd'); %or as appropriate for format you want displayed
plot(TimeDT, Displacement)
The ability to use datetime objects as the "x" values did not start with R2014b with the rest of the Handle Graphics 2 (HG2) graphics system, so if you are in the R2014b to R2015b range possibly it was not yet available.
  4 个评论
Walter Roberson
Walter Roberson 2017-9-14
You wrote, "instead of showing the time in julian time", so I took your word that what you have is indeed julian dates. However your values are instead consistent with datenum instead of julian dates. So in the code I posted replace 'juliandate' with 'datenum'

请先登录,再进行评论。

更多回答(0 个)

类别

Help CenterFile Exchange 中查找有关 Calendar 的更多信息

Community Treasure Hunt

Find the treasures in MATLAB Central and discover how the community can help you!

Start Hunting!

Translated by